Finding the steel added between bid and construction drawings

How to compare bid and construction drawings sheet by sheet, weigh each rebar change and claim the right extra.

Between drawings issued for bid and drawings issued for construction, the engineer often changes the rebar: one more bar, a tighter spacing, an added beam. Every change left unclaimed is steel supplied without being paid.

1. Gather the right documents

  • The bid set and all its addenda: a change already published by addendum was part of the price.
  • The complete construction set, with the date and revision of each sheet.
  • The bid takeoff, to know what was counted.

2. Match the sheets

Pair each construction sheet with the same bid sheet by its number and title. Added sheets are steel added in full; removed sheets are a credit.

3. Compare element by element

  • Bars: count, size, length, hooks, laps.
  • Spacing: a 10M @ 400 that becomes @ 300 adds a third more bars.
  • Stirrups and ties: they often weigh more than expected.
  • Concrete dimensions: a thicker slab or a higher wall lengthens the bars.

4. Weigh without scaling

Every weight should come from a written dimension or a calculation made from written dimensions: length × mass per metre of the bar size. A scaled measurement can be disputed; a dimension cannot.

5. Present the extra

For each sheet: what changed, the weight, then the total per bar size. Attach the calculation details: that is what gets a claim accepted.

Teyvor Rebar does this sheet-by-sheet comparison and produces this report, with the calculation details, in 15 to 40 minutes.

Try it on your own drawings

One free comparison on your own drawings, no card.