How to price a rebar change directive
Change directive, change notice, change order: how to isolate the steel added or removed against the drawings in force, without missing anything.
A directive changes drawings already in force. The right price compares the directive with the previous state of the same element, not with the original bid.
The two cases
- A directive that changes: compare each directive sheet with the latest revision in force of the same sheet. Only the difference is claimed.
- A directive that adds a new element (a pit, a pad, a slab): all the steel drawn is added at 100%.
What is most often missed
- The stirrups and ties of a changed beam.
- Laps and anchorages that get longer when the bar size changes.
- Tie bars and steel chairs.
- Sheets affected indirectly: a changed section often changes the plan.