How to price a rebar change directive

Change directive, change notice, change order: how to isolate the steel added or removed against the drawings in force, without missing anything.

A directive changes drawings already in force. The right price compares the directive with the previous state of the same element, not with the original bid.

The two cases

  • A directive that changes: compare each directive sheet with the latest revision in force of the same sheet. Only the difference is claimed.
  • A directive that adds a new element (a pit, a pad, a slab): all the steel drawn is added at 100%.

What is most often missed

  • The stirrups and ties of a changed beam.
  • Laps and anchorages that get longer when the bar size changes.
  • Tie bars and steel chairs.
  • Sheets affected indirectly: a changed section often changes the plan.

Deadlines

Contracts often set a deadline to price a directive. The faster the pricing, the easier it is to get it accepted before fabrication.